Analysis: Cuba looks beyond US for wind alliances
1 December 2014 by Luis Ini
CUBA: Cuba's government has set itself the target of supplying 24% of
its electricity needs from renewables by 2030 as part of a plan to
attract foreign investment.
Renewables currently only provide 4%, with wind contributing 0.1%.
Cuba's wind capacity totals just 11.7MW installed in four projects.
Development has been hampered by the US trade embargo in force since the
Cuban revolution in 1960.
Speaking to Windpower Monthly, Antonio Valdés Delgado,Cuban executive
secretary of the sustainable development programme for renewable energy
sources, said the embargo made it harder for Cuba to build wind capacity
than for any other country in the Latin American/Carribbean region.
Despite the proximity of the US and the overcapacity in its
manufacturing, Cuba's four projects use technology from as far afield as
France, Spain and China. Turiguano Island, a 450kW demonstration project
built in 1997 uses Ecotecnia turbines, while the 1.65MW Los Canarreos
project installed Vergnet turbines (2007). The most recent developments
have used Goldwind turbines: the 9.6MW Gibara I (2008) and 4.5MW Gibara
II projects (2010).
Speaking about plans to bring in foreign investment, Valdés Delgado said
that "wind manufacturing could offer Cuba's industry the opportunity to
establish alliances with overseas partners".
Official studies suggest that the country's wind energy potential is
between 1.2GW and 3.5GW. More than 32 areas of the country have been
examined by consultants including DNV GL. "From the available wind
resource, Union Electric [the state-owned electricity distribution
company] has studied and planned to install 633MW in 13 wind farms with
capacity factors above 30%, thus resulting in more than 1 TWh/year and
prevent the emission of more than 900,000 tonnes of CO2."
Planned projects
Among planned projects, 13 are expected to be installed in the east of
the island, 11 with a capacity of 51MW each and the other two at 36MW
each. One project, located in the province of Las Tunas, signed a 51MW
deal with Goldwind in December. These machines are set to be installed
next month.
Maybe, the most ambitious project proposed is Maisí wind farm, in the
far east of the island, to install 174MW in total acrossfour phases:
Punta Quemado 1 and 2 (51MW and 36MW each), and Punta Fraile 1 and 2
(51MW and 36MW each).
At present, with total installed power of almost 6GW, Cuba is highly
dependent on fossil fuels for the production of electricity. Over 50% of
the fuel used is imported, representing 96.2% of energy consumption. "We
are looking for to reduce the inefficiency of the electrical system, the
dependence on fossil fuels and the high cost of energy that is delivered
to consumers," said Valdés Delgado.
In total, the plan for foreign investment in renewable energy hopes to
reach 2.1GW by 2030. This includes the installation of 755MW through 19
bioelectrical plants, 700MW in solar farms connected to the national
power grid and 74 small hydropower plants with more than 56MW.
Source: Analysis: Cuba looks beyond US for wind alliances | Windpower